Channel tunnel investigation undertaken by James Fisher Strainstall

Overview

James Fisher Strainstall (JF Strainstall) was contracted by Balfour Beatty Utility Solutions to understand the behaviour of diesel exhaust fumes in turbulent airflow within the Channel Tunnel in London.

 

Challenge

The generators were mounted on a specially modified carriage used to install high voltage HV cables.

The test results were used to develop health and safety procedures to mitigate worker exposure to exhaust emissions including NOx and particulates. 

 

Solution

JF Strainstall installed four anemometers to measure wind speed on the custom-built track vehicle, while other contractors measured emission levels.

The generators were run at different loads to determine how emission levels in the tunnel varied. In addition, measurements were taken with the ventilation fans turned off.

The system was fully automated and GPS time synchronised to ensure consistency of data, also making the process quicker and easier.

The project brief was unique, but the JF Strainstall engineers used their extensive experience and technical expertise to deliver a tailored solution that seamlessly integrated with the work of the other contractors.

JF Strainstall
Registered office: Fisher House, PO Box 4, Barrow-in-Furness, Cumbria, LA14 1HR, UK Registered in England no. 4042929 E: enquiries@jf-strainstall.com